Mold Trial Checklist: What to Verify at T0 Before Approving Steel Changes

Mold Trial Guide

A mold trial checklist turns the T0 trial into a decision, not a photo session. Its job is to prove the tool can fill the cavity and eject a part worth measuring. Before the press runs, agree in writing what T0 must prove, which samples count, and who signs off on steel changes. That written agreement is the whole checklist in one line.

T0 is the first trial of a new mold. T0 samples are diagnostic, not production parts.

A Mold Trial Checklist Starts Before the Press Runs

T0, T1, and T2 are project labels, not universal standards, so define each trial in the purchase order. One shop calls the first shots T0. Another calls the same run T1. A third uses T0 for a dry run with no plastic at all. None of these labels is wrong. The mistake is assuming your supplier uses the same one you do.

Name the objective of each trial, the sample count, the inspection scope, the report contents, and the person who makes the call. Ask the supplier to cut uncertain features steel-safe. Removing steel after T1 is quick work. Adding steel back means welding, which costs days and can leave a mark on the part.

If your supplier cannot name the decision T0 must support, the trial will produce photos, not answers. Read the trial plan against the injection molding process guide for the project, so the trial matches the production intent.

Check the Mold Before the First Shot

The cheapest trial is the one with no plastic in it. Run the mold empty before any resin goes in. A dry run costs half a shift and finds the failures that ruin a trial. Watch every slide, lifter, and core move through its full stroke.

Check the ejection stroke and the way parts drop. Confirm cooling lines hold pressure with no leaks. If the mold uses a hot runner, confirm each zone heats and holds its set temperature. A cooling line that leaks water into the cavity does not show up as a puddle. It shows up as a silver streak on the part.

A mold that cannot run empty will not run full. Fix the binding lifter now. The same lifter will bind on shot one hundred, and by then the steel is harder to reach.

What Do the First Shots Tell You?

The first shots tell you whether the mold fills, releases, and holds its shape, not whether the part looks finished. Read the defects as a map, not as bad luck. A short shot points at flow or venting. Flash points at clamp or parting-line fit. A sink mark points at a thick section cooling last.

Keep the worst shot from the run, not the best one. The best shot hides the problem the mold still has. Label every sample with its cavity number and the shot it came from. A T0 sample is diagnostic evidence, not a production part, so judge it by what it reveals.

Do not chase cosmetics at T0. Polish and texture can wait until the mold fills and releases cleanly. Our weld line fixes cover the flow defects that show up here, and they start with gate position, not process tweaks.

Measure Only What the Drawing Calls Critical

The drawing decides what gets measured, not the sample box. Measure the critical features on cooled parts, after the parts reach room temperature. Parts keep shrinking as they cool. A dimension taken on a warm part will read differently the next morning.

Measure every critical feature on every cavity, or the report proves nothing about the mold. In a multi-cavity tool, one good cavity can hide a bad one. The report must show each cavity separately. Check fit and assembly with the real mating parts, not with a ruler alone. A clip that measures right can still fail to close.

Full measurement costs a day. A failed assembly in production costs a tool correction and a lost order. Our stable shot-to-shot process guide explains how a locked process window keeps those measurements repeatable.

Approve Steel Changes in Writing, One Issue at a Time

Turn the trial findings into a list. Each issue carries its defect, its location, a suspected cause, a proposed action, and an owner. Add one more field for the retest that proves the fix worked. Every steel change needs a named owner and a retest, or it will be cut twice.

Approve each change on its own. Never approve a verbal instruction to fix everything. Cutting steel away is quick. Welding steel back is slow, costly, and can leave a witness mark on the part. That is why uncertain features stay steel-safe until T1 proves the fit.

Ask for before-and-after photos of each correction at the next trial. Our DFM rules for gate placement show where gate changes usually start, and where they usually stop.

Frequently Asked Questions

What is a T0 mold trial?

A T0 mold trial is the first run of a new injection mold. The supplier mounts the tool, runs the planned resin through it, and produces the first physical parts. The trial checks mold action, filling, cooling, and ejection. T0 samples are diagnostic. They show what still needs correction before parts can be measured against the drawing.

How many parts should a T0 trial produce?

A T0 trial produces a short run, not a production batch. The run needs enough parts to show how each cavity fills and whether the defects repeat from shot to shot. A handful of labeled samples from every cavity beats a large box of unmarked parts. Agree the sample count in the trial plan.

Who decides whether a T0 trial passed?

The decision owner is named in the trial plan before the press runs. Usually that is the buyer’s project engineer, working from the agreed acceptance rule for each critical feature. The supplier proposes corrections and runs the next trial. The buyer approves the steel changes.

Should I approve steel changes after T0?

Approve only the corrections listed in the trial report, one by one. Each change needs a named owner and a retest at the next trial. Features that stay uncertain should stay steel-safe until T1 proves the fit. Welding steel back costs more time than cutting it away, and the weld can show on the part.

What should a T0 trial report include?

A usable T0 report names the mold, the part number, and the drawing revision. It records the resin grade, the machine, and the process settings used. It lists every defect with its cavity number and a photo. It ends with a correction list that names an owner and a retest for each issue.

The mold is ready for steel changes when every issue on the list has an owner and a retest. Until then, which item on your mold trial checklist still has no name beside it?